Expanding on-site

Supporting
customer growth
When Bunnings moved into Goodman's purpose-built 43,200 sqm distribution centre at Sydney's Eastern Creek over a decade ago, our customer knew that one day they would need more space.
As the Bunnings business grew, the need to expand became imminent. How could we find a way to keep our customer's busy facility operating, even as a much-needed extension took place?

Trading through expansion
Goodman’s team of experts worked hard to solve the problem. A 3-month design and programming process looked at how to manage extending the Bunnings facility by adding 12,399sqm of warehouse space, 2,670sqm of awnings, 7,200 sqm of hardstand and a 570kw solar system, and remove a 140m long, 13.5m high wall, all while allowing Bunnings to safely operate throughout.
Admittedly, there were some real challenges to be worked through. Our customer’s site is busy: deliveries starting from 4am, bringing a steady stream of traffic until around 9am and ruling out the quiet periods.
The site layout also meant separate construction access driveways were ruled out. However, for safety and operational reasons, we still needed a clear separation between construction vehicles (including the semi-trailers needed to bring in the long steel columns, rafters and roof sheets) and the Bunnings forklifts, their supplier’s trucks and the site’s general operational traffic. Plus, it all had to occur without holding up Bunning's operations.

Our experts’ innovative solution
Solutions began to emerge after Goodman posed a question to the builder, Qanstruct, about the order of construction. Instead of adding this extension from the building ‘out’, we asked: “Could they work in reverse? Start from the new end wall and work ‘back’ to the existing building?”
According to our experts, this would offer better options for traffic diversion, allow ease of movement for the build team and our customer, and even save time.
It worked. Over an 11-month build, open communication, combined with the new order of construction, meant Bunnings could continue to operate with minimal disruption, while expanding their facility to 55,600 sqm for the next phase of their business.